Heart of the City II, Sheffield | Heritage Demolition Case Study

Heart of the City II Sheffield City Council / Queensbury Sheffield
Heart of the City II Sheffield City Council / Queensbury Sheffield
Heart of the City II Sheffield City Council / Queensbury Sheffield
Heart of the City II Sheffield City Council / Queensbury Sheffield
Heart of the City II Sheffield City Council / Queensbury Sheffield
Heart of the City II Sheffield City Council / Queensbury Sheffield
Heart of the City II Sheffield City Council / Queensbury Sheffield
Heart of the City II Sheffield City Council / Queensbury Sheffield
Heart of the City II Sheffield City Council / Queensbury Sheffield
Heart of the City II Sheffield City Council / Queensbury Sheffield

CASE STUDY 6

Client

Sheffield City Council / Queensbury

Project type

Heritage Preservation / Regeneration

Building type

Mixed-use commercial buildings with retained Victorian Façade

Value of project

£800k

Timescale of project

10 months

SUMMARY OF PROJECT

As part of Sheffield’s £470 million Heart of the City II regeneration programme, TRD was appointed to carry out demolition works on a key city centre site, balancing modern development with heritage preservation. The project involved the removal of outdated commercial structures while retaining the Victorian façade of the former Athol Hotel, a locally significant architectural feature on Pinstone Street.

 

TRD’s work enabled the construction of Elshaw House, a new sustainable office building designed by Feilden Clegg Bradley Studios, which now anchors the development alongside Pound’s Park and Europe’s largest urban food hall.

Read more on Sheffield City Centre’s Strategic Vision here.

 

Our works involved:

 

  • Full demolition of blocks B and C, along with the internal structures behind the retained façade;

  • Structural support and protection of the Victorian frontage;

  • Deployment of Liebherr R 954 C demolition excavator for high-reach works;

  • Extensive hand demolition to protect heritage elements

  • Night working to minimise disruption in a high-footfall city centre;

  • Waste processing and recycling in line with environmental standards;

  • Coordination with heritage consultants, structural engineers, and city planners;

  • Site preparation for new-build construction including the construction of a piling mat.

Our specialist capabilities:

Retention of heritage Victorian facade, extensive hand demolition to protect heritage elements, night working, coordination with heritage consultants, local authorities, structural engineers and city planners.

 

Heritage Retention and Hand Demolition

The retained façade was a key planning condition and required exceptional care. TRD installed temporary steel bracing and worked closely with conservation specialists to protect the structure throughout.

Much of the demolition behind the façade was carried out by hand, allowing operatives to carefully dismantle internal walls, floors, and roof structures without compromising the integrity of the Victorian frontage. This method was essential in avoiding vibration damage and preserving original masonry and detailing.

Operatives used hand tools and small-scale equipment to remove materials in confined spaces, cataloguing key architectural features and ensuring safe separation from the demolition zone.

 

Machinery and Night Working

To dismantle the taller structures on site, TRD deployed its Liebherr R 954 C Litronic, a high-reach demolition excavator equipped with precision hydraulic attachments. The machine’s reach and stability were critical in navigating the tight urban footprint and working around the protected façade.

Due to the site’s location in a busy pedestrian zone, TRD also carried out night working operations, allowing progress to continue while reducing disruption to surrounding businesses, traffic, and residents. Noise control, dust suppression, and exclusion zones were implemented throughout.

 

Challenges and Execution

The combination of heritage retention, high-reach demolition, and manual dismantling required bespoke sequencing and constant communication between stakeholders. TRD coordinated with Sheffield City Council, conservation officers, and the design team to ensure every phase was executed safely and sensitively.

 

Outcome

TRD delivered the project on time and to specification, enabling the next phase of construction to begin without delay. The successful retention of the Victorian façade has been widely praised and now serves as a visual anchor for the Heart of the City II development.

TRD’s work exemplifies the balance between progress and preservation, supporting Sheffield’s transformation while honouring its architectural heritage